Gravel/Plumbing/Drainage
November 8, 2007
We have recently achieved a milestone—we secured the encroachment agreement from Colonial Pipelin (one that we have been working on that since June). We are starting the work on completing the road as we traverse the gas pipeline. Also, they are finishing up the plumbing work in the slab and we are installing the drainage system behind the building down the road to the youth building. We are planning on pouring the last footing this week and will start the electricians on their conduit installation in the slab next week. Hopefully we will be pouring the slab for the building the week after Thanksgiving.
Please be praying for the family of our friend, co-worker and project team member Al Moretz. He died suddenly last week of an apparent heart attack. All of the land development and design is his work and we are going to miss him and will continue to pray for his wife Cathy and their family.
|