Dam work, temporary power & foundation permit
September 27, 2007

We are continuing to move dirt from up front to the dam area to strengthen earthen dam and provide sewer access to the building. Also, we accomplished getting a crew trailer pulled in and temporary power provided down near the building pad. The big news is that we received our foundation permit and we will start digging and pouring footings next week.