Interior Work/Paving/Youth Building Start
May 21, 2008
Click Here |
 |
|
Inside Work, Duct Work, Electrical
March 7, 2008
Click Here
|
 |
|
Siding and Craft Work
February 21, 2008
Click Here |
 |
|
Steel Erection
January 30, 2008
Click Here |
 |
|
Beginning of erecting steel
January 10, 2008
Click Here |
 |
|
Road Work & Prep for Steel Erection
December 20, 2007
We have moved the steel from the front field area down to the building pad where it will be erected hopefully starting the week of 12/26. We have asphalted the entrance road all the way down to the building site—including new street signs for Bethlehem Church Street! |
|
Slab Pour
December 6, 2007
Click Here |
 |
|
Gravel/Plumbing/Drainage
November 8, 2007
Click Here |
 |
|
Curb, Gutters & Other Concrete
October 18, 2007
Click Here |
 |
|
Debris Cleanup/Continuing Footers
October 11, 2007
Click Here |
 |
|
Concrete Placement/First Concrete Pour
October 4, 2007
Click Here |
 |
|
Dam work, temporary power & foundation permit
September 27, 2007
Click Here |
 |
|
Site Drainage/Road Widening
September 20, 2007
Click Here |
 |
|
Land Development
September 6, 2007
Click Here |
 |
|
Building Pad & Road Development
August 30, 2007
Click Here |
 |
|
Land Prep
July 30, 2007
Click here |
 |
|
South Campus Groundbreaking Service
June 10, 2007
Click here for more pictures of this exciting event! |

|
| |
|
Elevations
Click Image to Enlarge |
|
|
|
| Site Plan |
|